DEPARTMENT  OF  THE  ARMY 

Sacramento  District,  CORPS  OF  ENGINEERS 
Williams  Resident  Office 
17800  S.  Camp  Williams 
Riverton,  UT  84065 


October  12,  2012  C-0512 

Subject:  Contract  No.  W912DR-10-C-0094;  Utah  Data  Center,  Camp  Williams,  Utah 
01  - Pay  Request  No.  49 

Balfour  Beatty/DPR/Big-D 

404  West  400  South 

Salt  Lake  City,  Utah  84101-1108 

Gentlemen, 

The  Government  has  received  and  reviewed  Pay  Request  No.  49.  The  Contractor 
requested  $15,897,313.69;  however  the  Government  is  paying  the  Contractor 
$13,893,792.92,  due  to  various  reasons,  as  stated  in  this  letter. 

The  Government  is  reducing  the  percentages  on  the  following  activities  due  to 
various  issues,  in  the  total  amount  of  $176, 1 86.50: 

1 . The  Government  pays  up  to  50%  of  the  activity  value  when  no  Initial  Inspection 
has  been  held: 

33C3592  RAF  Pedestal  L/O  @ Elec/Mech  Gallery  LI  SE  Quad  DCM3,  50% 
($1,188.50) 

2.  Preparatory  Meeting  has  not  been  held: 

32C610736  Instl  Lighting  Inverter  ME05  LI  NE  DCM2,  0%  ($138,092.00) 

3.  Wall  2 Wall  (Town  & Country  Flooring)  has  not  submitted  the  last  19  weeks  o 
Certified  payroll  to  the  Government  (06/09/2012,  06/16/2012,  06/23/2012, 
06/30/2012,  07/07/2012,  07/14/2012,  07/21/2012,  07/28/2012,  08/04/2012, 
08/11/2012,  08/18/2012,  08/25/2012,  09/01/2012,  09/08/2012,  09/15/2012, 
09/22/2012,  09/29/2012,  10/06/2012,  10/13/2012): 

23CO-0990  Install  VCT/Carpet  Flooring  - VCC,  0%  ($10,099.00) 

23CO-0993  Install  Rubber  Flooring  - VCC,  0%  ($7,800.00) 

26CO-0990A  Install  VCT  Flooring  in  Offices  (Grid  5 to  7)  - PWH  -LV0-ARA,  0% 
($4,105.00) 

26CO-0990B  Install  Rubber  Base  (Grid  5 to  8)  - PWH  - LV0-ARB,  0% 
($4,106.00) 

41CD3122  Rubber  Floor  Base  All  Areas  CPI , 0%  ($4,317.00) 

45CA1576  Rubber  Floor  Base  All  Areas  GP1,  0%  ($6,479.00) 


W91 2DR-1 0-C-0094 


C-0512 


The  Government  will  also  hold  $1 ,096,082.00  for  subcontractor  earnings  at  the 
request  of  BDB  (see  attached  letters  from  BDB  to  applicable  subcontractors). 

As  a result  of  BDB's  imposed  subcontractor  deductions,  please  reference  and  adhere 
to  FAR  Clause  52.232-27  Prompt  Payment  for  Construction  Contracts,  paragraph  (e) 
Subcontractor  Withholding  Procedures. 

The  activity  percentage  reductions  ($176,186.50),  along  with  BDB’s  requested 
subcontractor  deductions  ($1 ,096,082.00),  make  the  new  total  requested  amount  for  Pay 
Request  No.  49  $14,625,045.19. 

As  a result  of  the  project  being  behind  schedule  on  Deliverables  IB  and  2,  based  on 
the  schedule  submitted  with  Pay  Request  No.  48  and  the  subsequent  progress,  a 
retainage  of  5%  has  been  made  from  your  total  requested  amount.  The  Government  is 
retaining  5%  of  the  total  requested  amount  as  this  equates  to  10%  of  the  requested 
earnings  for  Deliverables  IB  and  2. 

The  Government  will  be  retaining  5%  from  the  total  requested  amount 
($14,625,045.19)  of  Pay  Request  No.  49,  in  the  amount  of  $731,252.27,  which  will  be 
released  at  a later  date.  Therefore,  the  Government  will  pay  the  Contractor 
$13,893,792.92,  for  Pay  Request  No.  49.  Similar  retainage  can  be  expected  on  future 
payment  requests  until  the  project  is  back  on  schedule  or  completed.  As  stated  above  in 
FAR  Clause  52.232-5,  “the  Contracting  Officer  may  retain  a maximum  of  10  percent  of 
the  amount  of  the  payment  until  satisfactory  progress  is  achieved.”  This  is  at  the 
discretion  of  the  Government  to  protect  its  interests  and  ensure  satisfactory  progress. 

The  above  mentioned  retainage  is  in  accordance  with  FAR  Clause  52.232-5 
Payments  Under  Fixed-Priced  Construction  Contracts,  paragraph  (e)  Retainage,  which 
reads  as  follows: 

(e)  Retainage.  If  the  Contracting  Officer  finds  that  satisfactory  progress  was 
achieved  during  any  period  for  which  a progress  payment  is  to  be  made,  the 
Contracting  Officer  shall  authorize  payment  to  be  made  in  full.  However,  if 
satisfactory  progress  has  not  been  made,  the  Contracting  Officer  may  retain  a 
maximum  of  10  percent  of  the  amount  of  the  payment  until  satisfactory  progress 
is  achieved.  When  the  work  is  substantially  complete,  the  Contracting  Officer 
may  retain  from  previously  withheld  funds  and  future  progress  payments  that 
amount  the  Contracting  Officer  considers  adequate  for  protection  of  the 
Government  and  shall  release  to  the  Contractor  all  the  remaining  withheld 
funds.  Also,  on  completion  and  acceptance  of  each  separate  building,  public 
work,  or  other  division  of  the  contract,  for  which  the  price  is  stated  separately  in 
the  contract  payment  shall  be  made  for  the  completed  work  without  retention  of 
a percentage. 

Analysis  of  your  current  progress  schedule,  submitted  with  Pay  Request  #48, 
indicates  a disparity  with  what  is  being  reported  in  the  various  UDC  Project  meetings 
(PDTs,  PLT,  ELT,  etc.).  The  current  progress  schedule  indicates  that  Deliverables  IB, 

2,  and  3 are  scheduled  to  finish  on  October  15,  2012,  December  24,  2012,  and  August 
8,  2013,  respectively.  Please  incorporate  accurate  logic  and  activity  durations,  for  each 
Deliverable,  into  the  schedule  and  submit  to  the  Government  with  the  next  pay  request 
(Pay  Request  #50).  This  is  in  accordance  with  the  agreement  made  by  Government  and 


W91 2DR-1 0-C-0094 


C-0512 


BDB  representatives  in  the  September  ELT  Meeting,  held  September  5,  2012.  This 
revised  schedule  will  be  used  as  the  final  baseline  schedule  for  the  remainder  of  the 
project.  All  changes  to  the  schedule  (logic,  durations,  etc.)  will  require  prior  approval 
from  the  Government.  If  an  acceptable  schedule  is  not  submitted,  the  Government 
reserves  all  its  rights  under  the  contract,  including  potential  denial  of  payment,  until  the 
project  schedule  accurately  reflects  each  Deliverable’s  completion  date. 


If  progress  is  not  complete  in  accordance  with  the  requirements  of  Deliverable  IB, 
the  government  is  authorized  to  asses  liquidated  damages  in  accordance  with  contract 
clause  52.21 1-12  in  the  amount  of  $53,585  for  each  calendar  day  of  delay. 


If  you  have  any  further  questions 
(801)  302-5022. 


or  concerns,  please  contact 


Administrative  Contracting  Officer 
Williams  Resident  Office 


Attachment  1 - Consolidated  Paving  & Concrete,  Inc. 
Attachment  2 - Green  Construction  Inc. 

Attachment  3 - Jacobson  Excavation,  LLC 


SAiiaCV*  P8AT7V  » OWt*  «0*1> 


Balfour  Beatty/DPR/Bfg-D,  a Joint  Venture 
P.O.  Box  1607 
Riverton,  UT  84065 
Phone:  801-253-5500 
Fax:  801-253-7210 


October  10,  2012 


Mr.  Jeremiah  Falslev 
Consolidated  Paving  & Concrete,  Inc. 
1705  W.  2450  South 
Ogden,  UT  84401 


Project 

Contract 

Classification 

Subject 


[11095]  Utah  Data  Center 

W912DR-10-C-0094 

Unclassified/For  Government  Use  Only 

Progress  Payments  Overstated  in  Owner  Pay  Application  #48 


Dear  Mr.  Falslev: 

Under  FAR  52.232-27  Prompt  Payment  for  Construction  Contracts  referenced  in  Attachment  5.5  of 
your  contract,  BDB  is  required  to  make  progress  payments  to  subcontractors  within  7 days  of 
receipt  of  owner  funds.  BDB  expects  funding  from  USACE  on  October  10,  2012  for  BDB  Pay 
Application  #48  representing  earnings  through  September  17,  2012. 

During  preparation  of  Pay  Application  #49,  BDB  reviewed  the  "in  place  progress"  of  your  activities 
and  realized  that  progress  reflected  in  Pay  Application  #48  was  overstated  in  terms  of  cost  % 
complete"  for  Consolidated  Paving.  Reference  Subcontractor  Earnings  Report  (SER)  #48 
enclosed  and  posted  to  your  Constructware  folder.  Since  BDB  may  not  hold  earned  monies 
unpaid  to  Subcontractors,  the  funds  earned  on  behalf  of  Consolidated  for  Pay  App  #48  have  been 
returned  to  USACE  on  Pay  App  #49.  Monies  associated  with  the  progress  variance  will  be  paid  to 
Consolidated  once  activity  progress  is  validated  with  BDB's  Superintendents  and  the  "cost  % 
complete"  advanced  accordingly. 


Specifically,  the  accounting  is  as  follows: 


• Total  Completed  and  Stored  as  shown  in  Pay  App  #48  $11,037,460 

• Total  Paid  as  of  October  9,  2012  $10,436,769 

e Funds  returned  to  USACE  in  Pay  Application  #49  $ 600,691 

No  action  is  required  on  your  part  relative  to  invoicing.  Please  validate  actual  progress  with  BDB's 
Superintendent.  You  are  welcome  to  email  me  at  bhendrickson@bdbiv.com  or  call  me  at 
801.381.6634  if  you  have  any  concerns  with  our  assessment. 


Sincerely, 


BALFOUR  BE ATTY/ DPR/ BIG-D,  A JOINT  VENTURE 

/ 


Bill  Hendrickson 
Project  Controls  Manager 


Joan  Williford  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 
Cyndee  Hadley  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 


Page  1 of  2 


TrrTT 


"i 


^^oj^elsorWBalfour  Beatty/DPR/Big-D,  a Joint  Venture) 
|^^HHHH^H[United  States  Army  Corps  of  Engineers) 

Correspondence  No.  02451 

Enclosures  Pay  App  #48  Consolidated  SER 


Supporting  Documents 


Document 

Type 

Document 

Open 

Description 

Date 

Size 

(KB) 

Doc 

11095-30685 

Pay  App  48  Consolidated  Paving  Inc 
SER 

10/10/2012 

141 

Page  2 of  2 


i 


sj  • nn  uh  i « vtn  i ut\ 

09  17  12  • 5ER  - CONSOLIDATED  PAVING,  INC  revl.xlsx 


UTAH  DA  TACENTEk  PROJECT.  CAMP  m~U/ 


IAPPUCATION  AMD  CERTIFICATE  FOR  PAYMENT 


[TO  Balfour  Beatty  | DPR  | Blg-D 

10427  North  1 1 170  West  (SR88) 
Lehi,  UT  84043 


[subcontractor: 
jADORESS 
|P0C 
Iphone  u 


Consolidated  Paving,  Inc 


{Contractors  APPLICATION  FOR  PAYMENT 


SUBCONTRACT  BUDGET 


01  General  (11095000) 


11  Site  (11095001) 


21  Admin.  (11095032) 


31  DCMs  (11095003) 


41  Chiller/Generatcr(l10S50G4) 


TOTALS 


|0T  General  (11095000) 


ORIGINAL 
CONTRACT 
SUM 


CHANGE  ORDERS 
SCHEDULED 
VALUE 


REVISED 

CONTRACT 

SUM 


$8,982,816.00 


064, 273.8S  f 81 1 ,057,088.86  ] 


PAYMENT  APPLICATION 


COMPLETED  AND  STORED 


ORIGINAL  CONTRACT 

COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


CHANGE  ORDERS 
COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


TOTAL 
COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


11  Site  (11095001) 


21  Adrrun  (11095C02) 


31  DCMs  (11095003) 


41  Cniller/Generatar  (11C95004) 


TOTALS 


$8,986,614.00 


I hearty  certify,  to  the  best  of  my  Knowledge  and  belief  that  - 

the  Work  covered  by  this  Application  for  Payment  has  been  completed  in  accordance  with 
[the  Subcontract  Documents,  that  all  amounts  have  been  paid  by  the  Contractor  for  Work  for  which 
previous  Certificates  for  Payment  were  issued  and  payments  received  from  the  Contractor  (BDB),  and 
(that  current  payment  shown  herein  ts  now  due 


Subcorrt  rector 


BY: 


Date 


Form  updated  Sept  28.  2012 


fM^cmsexnY  •.om  » wm> 


Balfour  Beatty/DPR/Big-D,  a Joint  Venture 
P.O.  Box  1607 
Riverton,  UT  84065 
Phone:  801-253-5500 
Fax:  801-253-7210 


October  10,  2012 

Mr.  Micah  Green 
Green  Construction  Inc. 

903  West  Center  Street 
Building  D 

North  Salt  Lake,  UT  84054 
USA 

Project 
Contract 
Classification 

Subject 

Dear  Mr.  Green: 

Under  FAR  52.232-27  Prompt  Payment  for  Construction  Contracts  referenced  in  Attachment  5.5  of 
your  contract,  BDB  is  required  to  make  progress  payments  to  subcontractors  within  7 days  of 
receipt  of  owner  funds.  BDB  expects  funding  from  USACE  on  October  10,  2012  for  BDB  Pay 
Application  #48  representing  earnings  through  September  17,  2012. 

During  preparation  of  Pay  Application  #49,  BDB  reviewed  the  "in  place  progress"  of  your  activities 
and  realized  that  progress  reflected  in  Pay  Application  #48  was  overstated  in  terms  of  "cost  % 
complete"  for  Green  Construction.  Reference  Subcontractor  Earnings  Report  (SER)  #48  enclosed 
and  posted  to  your  Constructware  folder.  Since  BDB  may  not  hold  earned  monies  unpaid  to 
Subcontractors,  the  funds  earned  on  behalf  of  Green  for  Pay  App  #48  have  been  returned  to 
USACE  on  Pay  App  #49.  Monies  associated  with  the  progress  variance  will  be  paid  to  Green  once 
activity  progress  is  validated  with  BDB's  Superintendents  and  the  "cost  % complete"  advanced 
accordingly. 

Specifically,  the  accounting  is  as  follows: 

• Total  Completed  and  Stored  as  shown  in  Pay  App  #48  $17,184,303 

• Total  Paid  as  of  October  9,  2012  $16,839,168 

• Funds  returned  to  USACE  in  Pay  Application  #49  $ 345,135 

No  action  is  required  on  your  part  relative  to  invoicing.  Please  validate  actual  progress  witti  BDB's 
Superintendent.  You  are  welcome  to  email  me  at  bhendrickson® bdbiv.com  or  call  me  at 
801.381.6634  if  you  have  any  concerns  with  our  assessment. 


[11095]  Utah  Data  Center 
W912DR-10-C-0094 
Unclassified/For  Government  Use  Only 

Progress  Payments  Overstated  in  Owner  Pay  Application  #48 


Sincerely, 


BALFOUR  BEATTY/ $PR/BIG-D,  A JOINT  VENTURE 


Bill  Hendrickson 
Project  Controls  Manager 


Page  1 of  2 


cc 


Joan  Williford  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 
Cyndee  Hadley  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 
Leon  Nelson  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 
Robert  Mecklenburg  (United  States  Army  Corps  of  Engineers) 

Correspondence  No.  02449 

Enclosures  Pay  App  #48  Green  SER 


Supporting  Documents 


Document  Type 

Document 

Open 

Description 

Date 

Size  (KB) 

Doc 

11095-30682 

m pi 

Pay  App  48  Green  SER 

10/10/2012 

163 

■i 


Page  2 of  2 


APPLICATION  AND  CERTIFICATE  FOR  PAYMENT 
TO  Balfour  Beatty  | DPR  | Blfl-D 

10427  Morth  11170  West  (SR88} 

LfiW.  lit  8404 3 


SUBCONTRACTOR 
ADORE SS 
POC 

PHONE  # 


oreen  Construction 


Contractor's  APPLICATION  FOR  PAYMENT 


SUBCONTRACT  BUDGET 


01  General  (11095000) „ 

11  Site  (110950011 

21  Ad rnn  (110950021 

31  DCMs  (11095003) 

^IChlltetGenerator^lOSSOO^ 
TOTALS  ____ 


ORIGINAL 

CONTRACT 

SUM 


$13,420,000.00 


PAYMENT  APPLICATION 

COMPLETED  AND  STORED 

01  General  (11095000) 

11  Site  (1109S0Q1) 

21  Admin  (11095002)  

31  DCMs  (11095003) _ 

41  ChiHer/G€nerator(11C95004) 
TOTALS 


ORIGINAL  CONTRACT 
COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


CHANGE  ORDERS 
SCHEDULED 
VALUE 


REVISED 

CONTRACT 

SUM 


$3,875,877^3  | >17,395.677.13 


CHANGE  ORDERS 
COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


TOTAL 

COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


$13,378,167.80 


,808,135.13  $17,184,302.73 


I heart)-/  certify,  to  the  best  of  my  knowledge  and  belief  that  - 

the  WorK  covered  by  this  Application  for  Payment  has  beer  completed  in  accordance  with 
the  Subcontract  Documents,  that  ail  amounts  have  been  paid  by  the  Contractor  for  Work  for  which 
previous  Certificates  for  Payment  were  issued  and  payments  received  from  the  Contractor  (BDB),  and 
that  current  payment  shown  herein  is  now  due 

I Subcontractor 


IForm  u 


1 21  2012 


APPLICATION  NO:  48 

BILUNG  PERIOD  TO:  9/17/2012 

CONTRACT  NO:  11095003 

CONTRACT  DATE: 

JOB  ff:  11085000;  11095001;  11095002;  11096003;  11096004 

Application  ts  made  for  Payment,  as  shown  below,  in  connection  with  the 
Contract 

Continuation  Sheets)  are  attached 

1.  ORIGINAL  CONTRACT  SUM 

2.  NET  CHANGE  ORDERS  TO  DATE 

3.  CONTRACT  SUM  TO  DATE  (Une  #1  & U2  above) 

4 TOTAL  COMPLETED  & STORED  TO  DATE 


Distribution  to: 

X Contractor 
X Contractor's  Rep 
X Subcontractor 
Architect 


5 RETAINAGE: 

% of  Completed  Work 

(Column  I)  varies 

8.  TOTAL  EARNED  LESS  RETAINAGE 

(Line  4 Less  Line  5 Totals) 

7 LESS  PREVIOUS  CERTIFICATES  FOR 

PAYMENT  (Une  6 from  pnor  Certificate) 

8.  CURRENT  PAYMENT  DUE 

9.  BALANCE  TO  FINISH,  PLUS  RETAINAGE 

(Line  3 Ies6  Line  6) 


17.173.467  43 


$10,816.30 

$211,37440 


acATIY  • &PX  # &&•%> 


Balfour  Beatty/OPR/Big-D,  a Joint  Venture 
P.O.  Box  1607 
Riverton,  UT  84065 
Phone:  801-253-5500 
Fax:  801-253-7210 


October  10,  2012 

Mr.  Blair  Peacock 
Jacobson  Excavation  LLC 
579  East  Fremont  Way 
Elk  Ridge,  Utah  84651 

Project 
Contract 
Classification 

Subject 

Dear  Mr.  Peacock; 

Under  FAR  52.232-27  Prompt  Payment  for  Construction  Contracts  referenced  in  Attachment  5.5  of 
your  contract,  BDB  is  required  to  make  progress  payments  to  subcontractors  within  7 days  of 
receipt  of  owner  funds.  BDB  expects  funding  from  USACE  on  October  10,  2012  for  BDB  Pay 
Application  #48  representing  earnings  through  September  17,  2012. 

During  preparation  of  Pay  Application  #49,  BDB  reviewed  the  "in  place  progress"  of  your  activities 
and  realized  that  progress  reflected  in  Pay  Application  #48  was  overstated  in  terms ; of  cost  /o 
complete"  for  Jacobsen  Excavation.  Reference  Subcontractor  Earnings  Report  (SER)  #48 
enclosed  and  posted  to  your  Constructware  folder.  Since  BDB  may  not  hold  earned  monies 
unpaid  to  Subcontractors,  the  funds  earned  on  behalf  of  Jacobsen  for  Pay  App  #48  have  been 
returned  to  USACE  on  Pay  App  #49.  Monies  associated  with  the  progress  variance  will  be  paid  to 
Jacobsen  once  activity  progress  is  validated  with  BDB's  Superintendents  and  the  cost  % 
complete"  advanced  accordingly. 

Specifically,  the  accounting  is  as  follows; 

• Total  Completed  and  Stored  as  shown  in  Pay  App  #48  $2,806,512 

• Total  Paid  as  of  October  9,  2012  $2,556,256 

• Funds  returned  to  USACE  in  Pay  Application  #49  $ 150,256 

No  action  is  required  on  your  part  relative  to  invoicing.  Please  validate  actual  progress  with  BDB  s 
Superintendent.  You  are  welcome  to  email  me  at  bhendrickson@bdb1v.cprn  or  call  me  at 
801.381.6634  if  you  have  any  concerns  with  our  assessment. 


[11095]  Utah  Data  Center 

W912DR-10-C-0094 

Unclassified/For  Government  Use  Only 

Progress  Payments  Overstated  in  Owner  Pay  Application  #48 


Sincerely, 

BALFOUR  BEATTy/DPR/BIG-D,  A JOINT  VENTURE 


Project  Controls  Manager 

cc  Joan  Williford  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 

Cyndee  Hadley  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 


Page  1 of  2 


Leon  Nelson  (Balfour  Beatty/DPR/Big-D,  a Joint  Venture) 

(United  States  Army  Corps  of  Engineers) 


Correspondence  No.  02450 

Enclosures  Pay  App  #48  Jacobson  SER 

Supporting  Documents 


Document 

Type 

Document 

Open 

Description 

Date 

nsm 

Doc 

11095-30683 

Pay  App  48  Jacobson  Excavation 

SER 

10/10/2012 

138 

Page  2 of  2 


i i: 


VJ  mu  UMirt  utificn 


09-17-12  SER-  JACOBSON  EXCAVATION.xIsx 


APPUCATION  AND  CERTIFICATE  FOR  PAYMENT 

TO  Balfour  Beatty  | DPR  I Blg-0 

10427  North  11170  West  (SR88) 

Lehl,  UT  04043 


WTicn  rnutfvv • , 


SUBCONTRACT: 

address 

POC; 


PHONE# 


Jacobson  Excavation 


Contractor's  APPLICATION  FOR  PAYMENT 


liCT  BUDGET 


01  General  (11095000) 

11  Site  (11095001) 

21  Admin  (11085002) 

31  OCMafl  1095003) 

4lChilter/Gencrator  (11095004 
TOTALS 


ORIGINAL 

CONTRACT 

SUM 


S2. 205.208.00 


PAYMENT  APPUCATION 

COMPLETED  AND  STORED 

01  General  (11C950C0) 

11  Site  (1 10950011 

21  Admin  fl  1095002) 

31  DCMS  (11095003) 

41  Chiller/Generalor  (11095C04) 

TOTALS  


ORIGINAL  CONTRACT 
COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


CHANGE  ORDERS 
SCHEDULED 
VALUE 


REVISED 

CONTRACT 

SUM 


$808,103,28  82,813,309.26 


CHANGE  ORDERS 

COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


TOTAL 

COMPLETED  AND 
STORED 

TOTAL  TO  DATE 


$2,198,408,00 


$808,103.26  $2,808,612.26 


t hearty  oertrfy.  to  the  best  of  my  knowledge  and  belief  that  - 

the  Work  covered  by  thie  Application  for  Payment  has  been  completed  in  accordance  with 
the  Subcontract  Documents,  that  all  amounts  have  been  paid  by  the  Contractor  for  Work  for  which 
previous  Certificates  for  Payment  were  issued  and  payments  received  from  the  Contractor  (BDB),  and 
that  current  payment  shown  herein  is  now  due 


j Subcontractor 


APPLICATION  NO:  48 

BILLING  PERIOD  TO:  9/1 7/201 2 

CONTRACT  NO:  11096000 

CONTRACT  OATE: 

JOB#:  11 09 6000;  11085001;  11095002;  11096003;  11096004 

Application  Is  made  for  Payment,  as  shown  below,  in  connection  with  the 
Contract 

Continuation  Sheet(s)  are  attached 
1 ORIGINAL  CONTRACT  SUM 

2.  NET  CHANGE  ORDERS  TO  DATE 

3.  CONTRACT  SUM  TO  DATE  (Line  #1  & #2  above)  » g 

4.  TOTAL  COMPLETED  & STORED  TO  DATE 

5 RETAINAGE 

% of  Completed  Work 

(Column  I)  vanes 

6 TOTAL  EARNED  LESS  RETAINAGE 

(Line  4 Less  Line  5 Totals) 

7 LESS  PREVIOUS  CERTIFICATES  FOR 

PAYMENT  (Line  6 from  plor  Certificate) 

8.  CURRENT  PAYMENT  DUE 
9 BALANCE  TO  FINISH,  PLUS  RETAINAGE 
(Line  3 less  Line  6) 


$2.761.720.26 

$44,792.00 

$6,797.00 


Distribution  to: 

X Contractor 
X Contractor's  Rep 
X Subcontractor 
Architect 


State  of  County  of. 

Subscribed  and  sworn  to  before  me  this  day  of 
Notary  Public. 

My  Commission  Number 
My  Commission  expires